PROJECTS

Taman Crude Oil Loading Terminal

Customer
Tamanneftegaz
Year
2014-2019
Location
Russia
Electric Heating Systems
Total cable length118 000 m
Total systems output6 200 kW
Heating Systems Application
  • Drain vessels
  • Pipelines
  • Oil and mazut farm (including 40 000 m3 tank)
Skin-Effect Heating Systems
Total length heated84 000 m
Number of feeding points13
Pipes diameterfrom 22 to 1,420 mm
Maintenance temperature+5 °C …+60 °C
Transported productsWater, liquefied hydrocarbon gas, oil, oil products

Vladimir Filanovsky Offshore Field

Customer
LUKOIL
Year
2015
Location
Russia
Electric Heating Systems
Total cable length14 500 m
Total systems output564 kW
Heating Systems Application
  • Oil and water pipelines
  • Oil and water tanks
  • Technical equipment

Ust-Luga Complex

Customer
NOVATEK
Year
2013
Location
Russia
Electric Heating Systems
Total cable length128 000 m
Total systems output6 100 kW
Heating Systems Application
  • Pipelines
  • Impulse lines
  • Water and fuel storage tanks

Urga Gas Field

Customer
ERIELL Group
Year
2012
Location
Uzbekistan
Electric Heating Systems
Total cable length 9 350 m
Total systems output 282 kW
Heating Systems Application
  • Pipelines

LUKOIL’s Volgograd Refinery

Customer
LUKOIL
Year
2019
Location
Russia
Electric Heating Systems
Total cable length 29 400 m
Total systems output 282 kW
Heating Systems Application
  • Tanks
  • Pipelines
  • Technical equipment

Vysotsk LNG Terminal

Customer
CryoGAS Group
Year
2018-2019
Location
Russia
Electric Heating Systems
Total cable length 16 673 m
Total systems output 300 kW
Heating Systems Application
  • 16 modular units
  • Tanks
  • Pipelines

Kumho Mitsui Chemicals Plant

Customer
Kumho Mitsui Chemicals, Inc.
Year
2009
Location
Korea
Electric Heating Systems
Total length heated15 000 m
Total system output 488 kW
Skin-Effect Heating Systems
Number of feeding points2
Pipes diameter159 mm
Maintenance temperature+20 °C
Transported productsNitrobenzol

Shchekinoazot Chemical Plant

Customer
Shchekinoazot Ltd.
Year
2011
Location
Russia
Electric Heating Systems
Total length heated 8 000 m
Total system output 410 kW
Heating Systems Application
  • Methanol M-450 producing plant
  • CFC and formalin producing plant
  • Impulse lines of Pervomayskaya power plant

The Bolshoi Theatre

Customer
Mosproject-2
Year
2011
Location
Russia
Electric Heating Systems
Total cable length3 576 m
Total systems output118 kW
Heating Systems Application
  • Roof: gutters, waterdrips, pipedrains

Luzhniki Palace of Sports

Customer
Metropolis Group
Year
2019
Location
Russia
Electric Heating Systems
Total cable length 8 680 m
Total systems output 392 kW
Heating Systems Application
  • Roof
  • Stairs & ramps
  • Indoor premises

ALROSA Udachny Mine

Customer
ALROSA
Year
2007-2015
Location
Russia
Electric Heating Systems
Total cable length 20 423 m
Total systems output 635 kW
Heating Systems Application
  • Pipelines of water and sewage systems
  • Tanks
  • Infrastructure

The terminal in the port of Vysotsk, Leningrad Region, is a complex multi-phased project for the production, storage, and export shipments of liquefied natural gas (LNG), operated by CryoGAS Group. The project is connected to the natural gas pipeline running from St. Petersburg to Vyborg and Russia’s national border.

The LNG terminal in Vysotsk comprises a branch gas pipeline, two liquefaction plants each capable of processing 40 tons of LNG per hour to a combined annual capacity of 660 000 tons, a 42 000 m3 LNG storage tank, as well as the required transport and shipment infrastructure, consisting of an LNG carrier handling facility at the sea berth and a tank truck handling facility.

The project will grow the share of Russian energy on the European markets and improve the environmental status of the Baltic Sea by switching shipping to LNG as bunker fuel.

SST Group was awarded the EPC turnkey contract for electric heating systems at the LNG project in Vysotsk. The scope of supply included engineering survey and design, procurement, start-up and commissioning. The design of the electric heating systems for the LNG terminal in Vysotsk took 8 500 man-hours. The installation work was completed by four engineers from SST Group and a team of twenty technicians. The combined length of the heating cables was 15.6 km. 13 km of power cables and 446 m3 of thermal insulation were used. 10 control cabinets were installed to control the electric heating systems. For Vysotsk LNG Terminal, cables of the premium series HTP, BTX and BTC by SST Group were specified.